8940 Military Department
Infrastructure Overview

The California Military Department's statewide facilities include 100 active armories, 4 aviation centers, 24 field maintenance shops, 2 combined support maintenance shops, and 2 maneuver area training equipment sites. The total real property assets of the Military Department encompass an area of 7.8 million square feet. These facilities are used to house and train the California National Guard and provide emergency public safety support. The California Military Department also operates three major training facilities consisting of troop lodging, administration, warehouse, maintenance, firing ranges, and maneuver training areas.


SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years.


Code State Building Program Expenditures Actual
2014-15*
Estimated
2015-16*
Enacted
2016-17*
6950 CAPITAL OUTLAY      
  Projects      
0000615 Military Department, Sacramento: Consolidated Headquarters Complex 125 8,831 6,889
Acquisition 125 8,831 -
Performance Criteria - - 6,889
0000703 Military Department: San Diego Readiness Center Renovation - 1,712 3,430
Preliminary Plans - 814 -
Working Drawings - 898 -
Construction - - 3,206
Equipment - - 224
0000705 Military Department, Sacramento: Advance Plans and Studies - 260 300
Study - 260 300
0000759 Military Department, San Bernardino: Sustainable Armory Renovation Program - 326 4,802
Preliminary Plans - 130 -
Working Drawings - 196 -
Construction - - 4,196
Equipment - - 606
0000760 Military Department, Ontario: Sustainable Armory Renovation Program - 2,188 -
Preliminary Plans - 88 -
Working Drawings - 130 -
Construction - 1,920 -
Equipment - 50 -
0000761 Military Department, Bakersfield: Sustainable Armory Renovation Program - 1,822 -
Preliminary Plans - 72 -
Working Drawings - 110 -
Construction - 1,590 -
Equipment - 50 -
0000917 Military Department, Eureka: Sustainable Armory Renovation Program - - 5,656
Performance Criteria - - 390
Design Build - - 5,266
0000918 Military Department, Escondido: Sustainable Armory Renovation Program - - 4,128
Performance Criteria - - 326
Design Build - - 3,802
0000919 Military Department, Santa Cruz: Sustainable Armory Renovation Program - - 4,012
Performance Criteria - - 302
Design Build - - 3,710
0000974 Military Department: Stockton Discovery Academy Youth ChalleNGe Program Dining Facility - - 2,600
Performance Criteria - - 295
Design Build - - 2,305
0000981 Military Department, Los Alamitos: Southern Region Emergency Operations Center Replacement - - 1,854
Preliminary Plans - - 570
Working Drawings - - 1,284
Total Expenditures (All Projects) $125 $15,139 $33,671

FUNDING Back to Top
Fund Code Fund Actual
2014-15*
Estimated
2015-16*
Enacted
2016-17*
0001 General Fund $ 125 $ 11,985 $ 19,907
0604 Armory Fund - - 2,600
0890 Federal Trust Fund - 3,024 11,014
0895 Federal Funds - Not In State Treasury - 130 150
Total Expenditures (All Funds) $ 125 $ 15,139 $ 33,671

Refer to the
Infrastructure Detail of Appropriations and Adjustments (pdf * - 3K) document for additional information.