The Department of Water Resources has two major infrastructure programs: the State Water Project and the flood control system in the Central Valley. The State Water Project is a water storage and delivery system that consists of 34 storage facilities, reservoirs, and lakes, 20 pumping plants, 4 pumping-generating plants, 5 hydroelectric power plants, and over 700 miles of canals, pipelines, and tunnels. The Project provides water to 25 million Californians and 750,000 acres of irrigated farmland. The Project also provides recreational opportunities to approximately 6 million visitors annually at 15 separate reservoir-based facilities as well as public fishing access to much of the Aqueduct. Existing flood control infrastructure in the Central Valley consists of 1,595 miles of levees, 348,000 acres of channels and floodways, over 800,000 linear feet of bank protection, over 60 mitigation and environmental restoration sites, and 55 various flood control structures including dams, weirs, pumping plants, diversion structures, gate structures, and drop structures. In general, these facilities provide more flood protection in urbanized areas and less in agricultural areas.


SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years.


Code State Building Program Expenditures Actual
2014-15*
Estimated
2015-16*
Enacted
2016-17*
3225 CAPITAL OUTLAY      
  Projects      
0000251 American River Flood Control Project: Common Elements 538 299 -
Construction 538 299 -
0000254 American River Watershed, Folsom Dam Raise Project 298 1,819 -
Construction 298 1,819 -
0000256 Butte Slough Outfall Gates Rehabilitation Project 1,635 11,020 -
Construction 1,635 11,020 -
0000259 Delta Flood Emergency Preparedness, Response, and Recovery Project 2,072 19,255 -
Construction 2,072 19,255 -
0000262 Feather River Early Implementation Project 984 - -
Construction 984 - -
0000263 Feather River Urban Flood Risk Reduction 57,978 3,873 -
Construction 57,978 3,873 -
0000264 Folsom Dam Modifications Project 14,998 26,908 -
Construction 14,998 26,908 -
0000265 Franks Tract Pilot Project 27,000 - -
Construction 27,000 - -
0000266 Frazier Creek/Strathmore Creek: Feasibility Study - 10 -
Study - 10 -
0000267 Knights Landing Outfall Gates Rehabilitation 340 4,166 -
Construction 340 4,166 -
0000268 Land Acquisition for Mitigation Bank(s) to Support Delta Levee Repairs - 1,094 -
Construction - 1,094 -
0000270 Lower Cache Creek, Yolo County, Woodland Area Project 164 461 -
Study 164 461 -
0000272 Lower San Joaquin River 62 245 -
Study 62 245 -
0000274 Marysville Ring Levee Reconstruction Project 240 8,396 -
Construction 240 8,396 -
0000277 Merced County Streams, Bear Creek Unit 31 1,176 -
Study 31 1,176 -
0000278 Mid-Valley Levee Reconstruction Project 59 239 -
Construction 59 239 -
0000281 Parcel Acquisition for Sutter Maintenance Yard 628 15 -
Acquisition 628 15 -
0000282 Perris Dam Remediation 6,185 30,634 -
Construction 6,185 30,634 -
0000283 Rock Creek/Keefer Slough: Feasibility Study - 237 -
Study - 237 -
0000286 Sacramento Yard--Soil and Groundwater Investigation and Remediation 712 2,264 -
Construction 712 2,264 -
0000289 South Sacramento County Streams 412 4,070 -
Construction 412 4,070 -
0000292 Sutter Basin Feasibility Study 90 357 -
Study 90 357 -
0000293 Sutter Bypass East Water Control Structures - 1 -
Construction - 1 -
0000296 System Evaluation of the State Plan of Flood Control - 1 -
Working Drawings - 1 -
0000297 Systemwide Levee Evaluations and Repairs 3,429 148,309 -
Construction 3,429 148,309 -
0000303 Water-Energy Efficiency Projects 2,028 17,972 -
Construction 2,028 17,972 -
0000304 West Sacramento Early Implementation Project 377 107,619 -
Construction 377 107,619 -
0000306 West Sacramento Project (GRR) 506 146 -
Study 506 146 -
0000307 West Stanislaus Feasibility Study - 17 -
Study - 17 -
0000308 White River/Deer Creek: Feasibility Study - 12 -
Study - 12 -
0000310 Yuba River Basin Project 5 450 -
Study 5 450 -
0000682 Various State Water Project 237,161 313,210 313,210
Various Items 237,161 313,210 313,210
0000743 Urban Flood Risk Reduction Program - 268,000 -
Construction - 268,000 -
0000744 Non-Urban Flood Risk Management - 118,000 -
Construction - 118,000 -
0000745 Systemwide Flood Risk Reduction Program - 300,000 -
Construction - 300,000 -
0000958 Salton Sea Management Plan - - 60,000
Study - - 8,000
Acquisition - - 6,000
Preliminary Plans - - 9,000
Working Drawings - - 6,000
Performance Criteria - - 1,000
Design Build - - 30,000
0000959 San Joaquin River Settlement Project - - 15,000
Study - - 100
Acquisition - - 100
Preliminary Plans - - 650
Working Drawings - - 2,000
Performance Criteria - - 150
Design Build - - 12,000
Total Expenditures (All Projects) $357,932 $1,390,275 $388,210

FUNDING Back to Top
Fund Code Fund Actual
2014-15*
Estimated
2015-16*
Enacted
2016-17*
0506 Central Valley Water Project Construction Fund $ 237,161 $ 313,210 $ 313,210
0995 Reimbursements 110 - -
3228 Greenhouse Gas Reduction Fund 2,028 17,972 -
6026 Bay-Delta Multipurpose Water Management Subaccount 17,000 - -
6031 Water Security, Clean Drinking Water, Coastal and Beach Protection Fund of 2002 10,000 - -
6051 Safe Drinking Water, Water Quality and Supply, Flood Control, River and Coastal Protection Fund of 2006 6,713 31,823 -
6052 Disaster Preparedness and Flood Prevention Bond Fund of 2006 84,920 1,027,270 -
6083 Water Quality, Supply, and Infrastructure Improvement Fund of 2014 - - 75,000
Total Expenditures (All Funds) $ 357,932 $ 1,390,275 $ 388,210

Refer to the
Infrastructure Detail of Appropriations and Adjustments (pdf * - 5K) document for additional information.