3540 Department of Forestry & Fire Protection
Infrastructure Overview
The Department of Forestry and Fire Protection operates over 500 facilities statewide, including 228 forest fire stations, 112 telecommunications sites, 39 conservation camps, 21 ranger unit headquarters, 16 administrative headquarters, 13 air attack bases, 9 helitack bases, 8 state forests, 2 nurseries, a training academy and various other miscellaneous facilities. These facilities support fire protection, the Office of the State Fire Marshall, and resource management efforts for over 31 million acres of state and privately owned wildlands throughout the state.
MAJOR PROJECT CHANGES Back to Top
- The Governor's Budget proposes $33.6 million in lease-revenue bonds to replace three fire stations.
SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years. The project phase and fund classification are also identified. The Standard Footnotes key can be accessed by clicking on any footnote link.
30 |
CAPITAL OUTLAY |
|
|
|
|
Major Projects |
|
|
|
30.10 |
COAST AREA |
$4,429 |
|
$4,611 |
|
$159,896 |
|
30.10.005 |
Alma Helitack Base--Relocate Facility |
- |
|
3 |
Ag |
7,236 |
WCn |
30.10.015 |
Ukiah Forest Fire Station--Replace Facility |
343 |
Cn |
47 |
WCgn |
- |
|
30.10.035 |
Stevens Creek Forest Fire Station--Replace Facility |
- |
|
2,727 |
Cn |
237 |
Cn |
30.10.065 |
Sweetwater Forest Fire Station--Relocate Facility |
89 |
Cn |
523 |
ACgn |
- |
|
30.10.090 |
Pacheco Forest Fire Station--Replace Facility |
536 |
Cn |
898 |
Cn |
- |
|
30.10.110 |
Elk Camp Forest Fire Station--Relocate Facility |
253 |
Cn |
- |
|
2,522 |
Cn |
30.10.125 |
Mendocino Ranger Unit Headquarters--Replace Automotive Shop |
125 |
Cn |
- |
|
3,520 |
Cn |
30.10.130 |
Santa Clara Ranger Unit Headquarters--Replace Automotive Shop |
- |
|
412 |
PWCgn |
- |
|
30.10.170 |
Santa Clara Unit Headquarters--Replace Facility |
1,334 |
Pn |
- |
|
19,522 |
WCn |
30.10.195 |
Las Posadas Forest Fire Station--Replace Facility |
146 |
Pn |
- |
|
4,595 |
PWCn |
30.10.210 |
San Mateo/Santa Cruz Unit Headquarters--Relocate Automotive Shop |
828 |
Pn |
- |
|
10,344 |
WCn |
30.10.215 |
Parlin Fork Conservation Camp--Replace Facility |
- |
|
- |
|
53,544 |
PWCn |
30.10.245 |
Soquel Fire Station--Replace Facility |
- |
|
- |
|
10,599 |
PWCn |
30.10.250 |
Felton Fire Station-Unit Headquarters--Replace Facility |
- |
|
- |
|
25,100 |
PWCn |
30.10.255 |
Mt. St. Helena Communication Facility--Renovation |
443 |
Cg |
1 |
Cg |
- |
|
30.10.265 |
North Region Forest Fire Station Facilities |
332 |
Wn |
- |
|
22,677 |
WCn |
30.20 |
CASCADE AREA |
$4,075 |
|
$107 |
|
$231,298 |
|
30.20.001 |
Fawn Lodge Forest Fire Station--Replace Facility and Install New Well |
94 |
Pn |
- |
|
6,484 |
PWCn |
30.20.006 |
Red Bluff Forest Fire Station/Unit Headquarters--Replace Forest Fire Station and Various Unit Headquarters Buildings |
3 |
Pn |
- |
|
24,482 |
PWCn |
30.20.007 |
Vina Helitack Base--Replace Facility |
924 |
Wn |
- |
|
12,138 |
WCn |
30.20.008 |
Westwood Forest Fire Station--Replace Facility |
114 |
Pn |
- |
|
5,534 |
PWCn |
30.20.015 |
Garden Valley Forest Fire Station--Replace Facility |
104 |
Pn |
- |
|
7,597 |
PWCn |
30.20.030 |
Harts Mill Forest Fire Station--Relocate Facility |
85 |
Agn |
9 |
Ag |
- |
|
30.20.045 |
Weaverville Forest Fire Station--Relocate Facility |
- |
|
98 |
Cn |
- |
|
30.20.050 |
El Dorado Fire Station-Service Warehouse |
- |
|
- |
|
26,375 |
PWCn |
30.20.120 |
Butte Unit Fire Station-Unit Headquarters--Replace Facility |
- |
|
- |
|
30,692 |
PWCn |
30.20.135 |
Intermountain Conservation Camp--Replace Facility |
1,010 |
Wn |
- |
|
19,164 |
WCn |
30.20.205 |
Higgins Corner Fire Station--Replace Facility |
69 |
Pn |
- |
|
9,209 |
PWCn |
30.20.230 |
Bieber Forest Fire Station/Helitack Base--Relocate Facility |
1 |
Pn |
- |
|
18,524 |
APWCn |
30.20.240 |
Siskiyou Unit Headquarters--Replace Facility |
1,669 |
Pn |
- |
|
30,062 |
WCn |
30.20.245 |
Ishi Conservation Camp--Replace Facility |
2 |
Pn |
- |
|
30,622 |
WCn |
30.20.250 |
Baker Fire Station--Replace Facility |
- |
|
- |
|
10,415 |
PWCn |
30.30 |
SOUTH AREA |
$4,173 |
|
$119 |
|
$221,832 |
|
30.30.015 |
Independence Forest Fire Station--Relocate Facility |
- |
|
72 |
Cn |
- |
|
30.30.020 |
San Luis Obispo Ranger Unit Headquarters--Replace Facility |
- |
|
- |
|
11,207 |
WCn |
30.30.025 |
Potrero Fire Station--Replace Facility |
- |
|
- |
|
10,389 |
PWCn |
30.30.065 |
San Marcos Forest Fire Station--Relocate Facility |
360 |
Cn |
- |
|
322 |
Cn |
30.30.075 |
Warner Springs Forest Fire Station--Replace Facility |
30 |
Cn |
- |
|
4,675 |
Cn |
30.30.090 |
Cuesta CC / San Luis Obispo Unit Auto Shop--Relocate Facility |
- |
|
- |
|
70,238 |
PWCn |
30.30.095 |
Cayucos Fire Station--Replace Facility |
- |
|
- |
|
9,678 |
PWCn |
30.30.115 |
Ventura Youth Conservation Camp--Construct Vehicle Apparatus Building, Shop, Warehouse |
30 |
Pn |
12 |
Pg |
3,089 |
WCn |
30.30.120 |
Fenner Canyon Conservation Camp--Construct Vehicle Apparatus, Office |
- |
|
3 |
Wg |
- |
|
30.30.150 |
Nipomo Forest Fire Station--Replace Facility |
561 |
WCg |
9 |
Pg |
- |
|
30.30.160 |
South Operations Area Headquarters--Relocate Facility |
- |
|
- |
|
42,594 |
AWCn |
30.30.165 |
Cuyamaca Forest Fire Station--Relocate Facility |
137 |
Wn |
23 |
ACgn |
937 |
Cn |
30.30.195 |
Miramonte Conservation Camp--Replace Facility |
2,970 |
Cn |
- |
|
47,565 |
Cn |
30.30.200 |
Paso Robles Forest Fire Station--Replace Facility |
85 |
Pn |
- |
|
7,917 |
PWCn |
30.30.220 |
Rincon Fire Station--Replace Facility |
- |
|
- |
|
13,221 |
PWCn |
30.40 |
SIERRA SOUTH |
$2,870 |
|
$6,310 |
|
$159,456 |
|
30.40.006 |
Pine Mountain Forest Fire Station--Relocate Facility |
- |
|
168 |
Ag |
9,994 |
PWCn |
30.40.007 |
Growlersburg Conservation Camp--Replace Facility |
- |
|
- |
|
43,147 |
WCn |
30.40.020 |
Batterson Forest Fire Station--Relocate Facility |
4 |
PWg |
4,370 |
WCg |
- |
|
30.40.030 |
Academy: Construct Dormitory Building and Expand Mess Hall |
- |
|
- |
|
9,343 |
Cn |
30.40.040 |
Hammond Forest Fire Station--Relocate Facility |
- |
|
86 |
WCgn |
- |
|
30.40.050 |
Rancheria Forest Fire Station--Replace Facility |
195 |
Pn |
7 |
PCgn |
- |
|
30.40.075 |
Usona Forest Fire Station--Replace Facility |
147 |
Cn |
139 |
PCgn |
- |
|
30.40.090 |
Antelope Forest Fire Station--Replace Barracks/Mess Hall |
- |
|
100 |
Cn |
- |
|
30.40.105 |
Vallecito Conservation Camp--Replace Utilities/Construct Apparatus Buildings |
- |
|
488 |
Cn |
- |
|
30.40.120 |
Dew Drop Forest Fire Station--Replace Facility |
26 |
Cn |
170 |
WCgn |
- |
|
30.40.125 |
Twain Harte Forest Fire Station--Relocate Facility |
29 |
Cn |
498 |
Cn |
- |
|
30.40.130 |
Springville Forest Fire Station--Relocate Facility |
17 |
Cn |
245 |
WCn |
- |
|
30.40.135 |
Raymond Forest Fire Station--Relocate Facility |
62 |
Wn |
16 |
WCn |
- |
|
30.40.145 |
Bautista Conservation Camp--Replace Modular Buildings |
27 |
Cn |
23 |
Cn |
- |
|
30.40.165 |
Tuolumne-Calaveras Service Center, Admin ECC--Relocate Facility |
- |
|
- |
|
24,655 |
PWCn |
30.40.170 |
Badger Forest Fire Station--Replace Facility |
- |
|
- |
|
3,744 |
Cn |
30.40.175 |
Parkfield Fire Station--Replace Facility |
- |
|
- |
|
7,209 |
PWCn |
30.40.185 |
Madera-Mariposa-Merced Unit HQ--Replace Facility |
1,723 |
Pn |
- |
|
26,782 |
WCn |
30.40.195 |
Altaville Forest Fire Station--Replace Facility |
59 |
PWn |
- |
|
4,746 |
WCn |
30.40.225 |
Altaville Forest Fire Station--Replace Automotive Shop |
581 |
Pn |
- |
|
7,971 |
WCn |
30.40.240 |
Gabilan Conservation Camp--Replace/Relocate Facilities |
- |
|
- |
|
21,865 |
PWCn |
30.60 |
STATEWIDE |
$112 |
|
$16,991 |
|
$32,068 |
|
30.60.041 |
Statewide--Replace Communications Facilities, Phase IV |
- |
|
1,098 |
PWg |
- |
|
30.60.045 |
Statewide--Construct Forest Fire Stations |
112 |
Pn |
- |
|
32,068 |
PWCn |
30.60.050 |
Statewide--Construct Communications Facilities |
- |
|
15,893 |
WCg |
- |
|
|
Totals, Major Projects |
$15,659 |
|
$28,138 |
|
$804,550 |
|
|
Minor Projects |
|
|
|
30.80 |
Minor Capital Outlay |
1,017 |
PWCg |
2,225 |
PWCg |
- |
|
|
Totals, Minor Projects |
$1,017 |
|
$2,225 |
|
$- |
|
Total Expenditures (All Projects) |
$16,676 |
|
$30,363 |
|
$804,550 |
|
FUNDING Back to Top
0001 |
General Fund |
$2,028 |
$24,096 |
$- |
0660 |
Public Buildings Construction Fund |
14,648 |
6,267 |
804,550 |
Total Expenditures (All Funds) |
$16,676 |
$30,363 |
$804,550 |
Refer to the Infrastructure Detail of Appropriations and Adjustments (pdf * - 4K) document for additional information.
|