3540 Department of Forestry, Fire Protection
Infrastructure Overview
The Department of Forestry and Fire Protection operates more than 530 facilities statewide, including 234 forest fire stations, 112 telecommunications facilities, 39 conservation camps, 21 ranger unit headquarters, 16 administrative headquarters, 12 air attack bases, 10 helitack bases, 8 state forests, 1 nursery, a training academy, and various other facilities. These facilities support fire protection, the Office of the State Fire Marshal, and resource management efforts for more than 31 million acres of state and privately-owned wildlands throughout the state.
SUMMARY OF PROJECTS Back to
Top Provides
expenditures for each major and minor capital project funded
in this state agency's budget for the past, current, and
budget years.
2485 |
CAPITAL OUTLAY |
|
|
|
|
Projects |
|
|
|
0000008 |
Garden Valley Forest Fire Station: Replace Facility |
6,800 |
- |
- |
|
Working Drawings |
289 |
- |
- |
|
Construction |
6,511 |
- |
- |
0000009 |
Academy: Construct Dormitory Building |
- |
977 |
12,625 |
|
Working Drawings |
- |
977 |
- |
|
Construction |
- |
- |
12,625 |
0000164 |
Altaville Forest Fire Station: Replace Automotive Shop |
865 |
- |
8,083 |
|
Preliminary Plans |
237 |
- |
- |
|
Working Drawings |
628 |
- |
- |
|
Construction |
- |
- |
8,083 |
0000165 |
Badger Forest Fire Station: Replace Facility |
1 |
4,362 |
- |
|
Construction |
1 |
4,362 |
- |
0000166 |
Baker Forest Fire Station: Replace Facility |
- |
125 |
774 |
|
Acquisition |
- |
125 |
- |
|
Preliminary Plans |
- |
- |
774 |
0000167 |
Bieber Forest Fire Station/Helitack Base: Relocate Facility |
-
1 |
98 |
1,452 |
|
Acquisition |
- |
80 |
- |
|
Preliminary Plans |
-
1 |
18 |
- |
|
Working Drawings |
- |
- |
1,452 |
0000169 |
Butte Ranger Unit Headquarters: Replace Facility |
2,100 |
10 |
30,784 |
|
Working Drawings |
2,100 |
10 |
- |
|
Construction |
- |
- |
30,784 |
0000170 |
Cayucos Forest Fire Station: Replace Facility |
382 |
668 |
- |
|
Preliminary Plans |
382 |
- |
- |
|
Working Drawings |
- |
668 |
- |
0000172 |
Fawn Lodge Forest Fire Station: Replace Facility and Install New Well |
5,839 |
- |
- |
|
Working Drawings |
25 |
- |
- |
|
Construction |
5,814 |
- |
- |
0000179 |
Las Posadas Forest Fire Station: Replace Facility |
17 |
4,774 |
- |
|
Working Drawings |
17 |
81 |
- |
|
Construction |
- |
4,693 |
- |
0000182 |
Parkfield Forest Fire Station: Relocate Facility |
- |
208 |
609 |
|
Acquisition |
- |
208 |
- |
|
Preliminary Plans |
- |
- |
609 |
0000185 |
Pine Mountain Forest Fire Station: Relocate Facility |
371 |
724 |
9,270 |
|
Preliminary Plans |
371 |
- |
- |
|
Working Drawings |
- |
724 |
- |
|
Construction |
- |
- |
9,270 |
0000186 |
Potrero Forest Fire Station: Replace Facility |
- |
- |
400 |
|
Acquisition |
- |
- |
400 |
0000188 |
Rincon Forest Fire Station: Replace Facility |
9 |
938 |
- |
|
Preliminary Plans |
9 |
938 |
- |
0000189 |
San Mateo/Santa Cruz Unit Headquarters: Relocate Automotive Shop |
1,092 |
- |
10,222 |
|
Preliminary Plans |
223 |
- |
- |
|
Working Drawings |
869 |
- |
- |
|
Construction |
- |
- |
10,222 |
0000192 |
Soquel Forest Fire Station: Replace Facility |
-
1 |
1,322 |
- |
|
Preliminary Plans |
-
1 |
554 |
- |
|
Working Drawings |
- |
768 |
- |
0000193 |
South Operations Area Headquarters: Relocate Facility |
1,566 |
44,227 |
- |
|
Acquisition |
- |
389 |
- |
|
Working Drawings |
1,566 |
- |
- |
|
Construction |
- |
43,838 |
- |
0000199 |
Vina Helitack Base: Replace Facility |
792 |
157 |
13,387 |
|
Preliminary Plans |
10 |
- |
- |
|
Working Drawings |
782 |
157 |
- |
|
Construction |
- |
- |
13,387 |
0000200 |
Westwood Forest Fire Station: Replace Facility |
34 |
362 |
6,250 |
|
Preliminary Plans |
34 |
- |
- |
|
Working Drawings |
- |
362 |
- |
|
Construction |
- |
- |
6,250 |
0000678 |
Paso Robles Forest Fire Station: Replace Facility |
169 |
7,057 |
- |
|
Working Drawings |
169 |
- |
- |
|
Construction |
- |
7,057 |
- |
0000680 |
Minor Projects |
266 |
3,742 |
1,247 |
|
Minor Projects |
266 |
3,742 |
1,247 |
0000712 |
San Luis Obispo Unit Headquarters Replacement |
- |
1,900 |
1,900 |
|
Preliminary Plans |
- |
1,900 |
- |
|
Working Drawings |
- |
- |
1,900 |
0000920 |
Statewide: Replace Communications Facilities, Phase V |
- |
- |
1,677 |
|
Preliminary Plans |
- |
- |
1,677 |
Total Expenditures (All Projects) |
$20,301 |
$71,651 |
$98,680 |
FUNDING Back to Top
0001 |
General Fund |
$
266 |
$
3,742 |
$
3,324 |
0660 |
Public Buildings Construction Fund |
20,035 |
65,676 |
93,456 |
0668 |
Public Buildings Construction Fund Subaccount |
- |
2,233 |
1,900 |
Total
Expenditures (All Funds) |
$
20,301 |
$
71,651 |
$
98,680 |
Refer to the
Infrastructure Detail of Appropriations and Adjustments (pdf * - 7K)
document for additional
information.
|