|
3860 Department of Water Resources
Infrastructure Overview
The Department of Water Resources has two major infrastructure programs: the State Water Project and the flood control system in the Central Valley. The State Water Project is a water storage and delivery system that consists of 34 storage facilities, reservoirs, and lakes, 20 pumping plants, 4 pumping-generating plants, 5 hydroelectric power plants, and over 700 miles of channels, canals and pipelines. The Project provides water to 25 million Californians and 750,000 acres of irrigated farmland. The Project also provides recreational opportunities to approximately 6 million visitors annually at 15 separate reservoir-based facilities as well as public fishing access to the entire Aqueduct. Existing flood control infrastructure in the Central Valley consists of 1 ,595 miles of levees, 348,000 acres of channels and floodways, over 800,000 linear feet of bank protection, over 60 mitigation and environmental restoration sites, and 55 various flood control structures including dams, weirs, pumping plants, diversion structures, gate structures, and drop structures. In general, these facilities provide more flood protection in urbanized areas and less in agricultural areas.
SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years. The project phase and fund classification are also identified. The Standard Footnotes key can be accessed by clicking on any footnote link.
01 |
CAPITAL OUTLAY |
|
|
|
|
Major Projects |
|
|
|
10.95 |
CONTINUING FORMULATION OF THE CALIFORNIA WATER PLAN |
$- |
|
$55,366 |
|
$- |
|
10.95.180 |
Franks Tract Pilot Project |
- |
|
27,000 |
CWb |
- |
|
10.95.200 |
Salton Sea Species Conservation Habitat Project |
- |
|
28,366 |
Cr |
- |
|
20.95 |
IMPLEMENTATION OF THE STATE WATER RESOURCES DEVELOPMENT SYSTEM |
294,206 |
Vn |
308,257 |
CVbn |
250,888 |
CVbn |
30.95 |
PUBLIC SAFETY AND PREVENTION OF DAMAGE |
$87,663 |
|
$567,848 |
|
$39,027 |
|
30.95.021 |
Feather River Early Implementation Project |
339 |
Cb |
58,557 |
Cb |
- |
|
30.95.022 |
Feather River Urban Risk Reduction Project |
- |
|
76,720 |
Cb |
- |
|
30.95.026 |
Land Acquisition for Mitigation Bank(s) to Support Delta Levee Repairs |
- |
|
1,094 |
AWPCb |
- |
|
30.95.027 |
Parcel Acquisition for Sutter Maintenance Yard |
- |
|
600 |
Ab |
- |
|
30.95.105 |
Marysville/Yuba Levee Reconstruction |
3 |
ACgr |
- |
|
- |
|
30.95.115 |
American River Flood Control Project Phase 1 - Common Elements |
8,272 |
ACbr |
1,405 |
Cbr |
- |
|
30.95.130 |
West Sacramento Project |
60 |
CSbr |
2,942 |
Cbr |
- |
|
30.95.135 |
West Sacramento Project (GRR) |
134 |
Sbr |
1,227 |
Sbr |
130 |
Sb |
30.95.140 |
Delta Flood Emergency Preparedness, Response, and Recovery Project |
5,258 |
Cb |
14,742 |
Cb |
12,000 |
Cb |
30.95.155 |
Mid-Valley Levee Reconstruction Project |
140 |
ACbr |
4,250 |
Cbr |
- |
|
30.95.160 |
West Sacramento Early Implementation Project |
249 |
ACb |
108,370 |
ACb |
- |
|
30.95.250 |
Yuba River Basin Project |
50 |
CSWbr |
1,043 |
Sbr |
- |
|
30.95.251 |
Marysville Ring Levee Reconstruction Project |
230 |
Cbr |
13,969 |
Cbr |
- |
|
30.95.260 |
South Sacramento County Streams |
6,113 |
ACWbr |
10,212 |
ACWbr |
- |
|
30.95.302 |
Sutter Basin Feasibility Study |
248 |
Sbr |
1,284 |
Sbr |
80 |
Sb |
30.95.305 |
Rock Creek-Keefer Slough Feasibility Study |
3 |
Sb |
401 |
Sbr |
- |
|
30.95.306 |
West Stanislaus Feasibility Study |
56 |
Sb |
705 |
Sbr |
- |
|
30.95.310 |
Lower Cache Creek, Yolo County, Woodland Area Project |
-63 |
Sb |
1,207 |
Sbr |
817 |
Sbr |
30.95.311 |
Folsom Dam Modifications Project |
39,805 |
ACbr |
61,073 |
Cbr |
25,759 |
Cbr |
30.95.314 |
Frazier Creek/Strathmore Creek Feasiblity Study |
3 |
Sb |
366 |
Sbr |
- |
|
30.95.315 |
White River/Deer Creek Feasiblity Study |
1 |
Sb |
385 |
Sbr |
- |
|
30.95.316 |
Merced County Streams Project Bear Creek Unit |
5 |
Sb |
3,470 |
CSbr |
- |
|
30.95.320 |
Lower San Joaquin River Regional Project |
262 |
Sb |
1,072 |
Sbr |
241 |
Sb |
30.95.327 |
Sacramento River Flood Control System Evaluation |
- |
|
333 |
Sb |
- |
|
30.95.328 |
American River Watershed, Folsom Dam Raise Project |
11 |
ACb |
3,350 |
Cbr |
- |
|
30.95.330 |
American River Watershed, Folsom Dam Raise Project, Bridge Element |
1 |
ACb |
- |
ACb |
- |
|
30.95.337 |
Butte Slough Outfall Gates Rehabilitation Project |
818 |
CWb |
13,777 |
CWb |
- |
|
30.95.340 |
Systemwide Levee Evaluations and Repairs |
15,392 |
ACPSWb |
176,464 |
ACPSWb |
- |
|
30.95.341 |
State-Federal Flood Control Evaluations |
6,790 |
Wb |
4 |
Wb |
- |
|
30.95.342 |
Sutter Pumping Plants' Control System |
1,634 |
ACb |
- |
ACb |
- |
|
30.95.343 |
Sutter Bypass East Water Control Structures |
181 |
CWb |
722 |
CWb |
- |
|
30.95.344 |
Knights Landing Outfall Gates Rehabilitation |
1,408 |
ACb |
4,746 |
ACb |
- |
|
30.95.345 |
Sacramento Yard-Soil and Groundwater Investigation and Remediation |
260 |
CWb |
3,358 |
CWb |
- |
|
|
Totals, Major Projects |
$381,869 |
|
$931,471 |
|
$289,915 |
|
Total Expenditures (All Projects) |
$381,869 |
|
$931,471 |
|
$289,915 |
|
FUNDING Back to Top
0001 |
General Fund |
$3 |
$- |
$- |
0506 |
Central Valley Water Project Construction Fund |
294,206 |
296,933 |
214,488 |
0995 |
Reimbursements |
15,515 |
59,571 |
7,871 |
3228 |
Greenhouse Gas Reduction Fund |
- |
- |
10,000 |
6026 |
Bay-Delta Multipurpose Water Management Subaccount |
- |
17,000 |
- |
6031 |
Water Security, Clean Drinking Water, Coastal and Beach Protection Fund of 2002 |
- |
10,000 |
- |
6051 |
Safe Drinking Water, Water Quality and Supply, Flood Control, River and Coastal Protection Fund of 2006 |
59 |
13,303 |
26,400 |
6052 |
Disaster Preparedness and Flood Prevention Bond Fund of 2006 |
72,086 |
534,664 |
31,156 |
Total Expenditures (All Funds) |
$381,869 |
$931,471 |
$289,915 |
Refer to the Infrastructure Detail of Appropriations and Adjustments (pdf * - 5K) document for additional information.
|