2665 High-Speed Rail Authority
Infrastructure Overview
The High-Speed Rail Authority is currently located in approximately 26,000 square feet of leased office space, most of which is in Sacramento. The Authority is actively acquiring real property and right-of-way accesses necessary for construction of the first section of the high-speed train system, extending from Madera to near Bakersfield. This system will eventually run between Anaheim and San Francisco, with extensions to Sacramento and San Diego.
MAJOR PROJECT CHANGES Back to Top
- The Governor's Budget proposes $250 million from the Greenhouse Gas Reduction Fund for the completion of environmental review and preliminary design for Phase 1 of the high speed train system ($58.6 million) and for right-of-way acquisition and construction on the Initial Operating Segment - Section 1 ($191.4 million).
SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years. The project phase and fund classification are also identified. The Standard Footnotes key can be accessed by clicking on any footnote link.
20 |
CAPITAL OUTLAY |
|
|
|
|
Major Projects |
|
|
|
20.01 |
Initial Operating Segment |
$105,851 |
|
$458,599 |
|
$1,270,129 |
|
20.01.010 |
Section 1 |
105,851 |
ABbf |
458,599 |
ABbf |
1,270,129 |
ABfs |
20.05 |
Planning - Acquisition and Design |
$- |
|
$109,979 |
|
$58,586 |
|
20.05.010 |
Planning - Acquisition and Design |
- |
|
109,979 |
ADf |
58,586 |
ADfs |
20.15 |
San Francisco to San Jose |
$11,085 |
|
$1,147 |
|
$- |
|
20.15.010 |
San Francisco to San Jose |
11,085 |
ADbf |
1,147 |
ADf |
- |
|
20.25 |
San Jose to Merced |
$5,363 |
|
$2,289 |
|
$- |
|
20.25.010 |
San Jose to Merced |
5,363 |
ADbf |
2,289 |
ADbf |
- |
|
20.30 |
Merced to Fresno |
$16,374 |
|
$4,101 |
|
$- |
|
20.30.010 |
Merced to Fresno |
16,374 |
ADbf |
4,101 |
ADbf |
- |
|
20.40 |
Fresno to Bakersfield |
$22,209 |
|
$8,442 |
|
$- |
|
20.40.010 |
Fresno to Bakersfield |
22,209 |
ADbf |
8,442 |
ADbf |
- |
|
20.45 |
Bakersfield to Palmdale |
$7,821 |
|
$6,591 |
|
$- |
|
20.45.010 |
Bakersfield to Palmdale |
7,821 |
ADbf |
6,591 |
ADbf |
- |
|
20.50 |
Palmdale to Los Angeles |
$13,198 |
|
$694 |
|
$- |
|
20.50.010 |
Palmdale to Los Angeles |
13,198 |
ADbf |
694 |
Af |
- |
|
20.60 |
Los Angeles to Anaheim |
$5,029 |
|
$496 |
|
$- |
|
20.60.010 |
Los Angeles to Anaheim |
5,029 |
ADbf |
496 |
ADf |
- |
|
20.70 |
Los Angeles to San Diego |
$8 |
|
$- |
|
$- |
|
20.70.010 |
Los Angeles to San Diego |
8 |
Ab |
- |
|
- |
|
20.80 |
Merced to Sacramento |
$- |
|
$961 |
|
$- |
|
20.80.010 |
Merced to Sacramento |
- |
|
961 |
Ab |
- |
|
20.90 |
Altamont Pass |
$1,947 |
|
$- |
|
$- |
|
20.90.010 |
Altamont Pass |
1,947 |
ADb |
- |
|
- |
|
20.99 |
Project Management and Agency Costs |
$24,197 |
|
$- |
|
$- |
|
20.99.010 |
Project Management and Agency Costs |
24,197 |
ADf |
- |
|
- |
|
|
Totals, Major Projects |
$213,082 |
|
$593,299 |
|
$1,328,715 |
|
Total Expenditures (All Projects) |
$213,082 |
|
$593,299 |
|
$1,328,715 |
|
FUNDING Back to Top
0890 |
Federal Trust Fund |
$185,805 |
$571,325 |
$1,078,715 |
3228 |
Greenhouse Gas Reduction Fund |
- |
- |
250,000 |
6043 |
High - Speed Passenger Train Bond Fund |
27,277 |
21,974 |
- |
Total Expenditures (All Funds) |
$213,082 |
$593,299 |
$1,328,715 |
Refer to the Infrastructure Detail of Appropriations and Adjustments (pdf * - 5K) document for additional information.
|