5225 Corrections and Rehabilitation
Infrastructure Overview
The California Department of Corrections and Rehabilitation (CDCR) operates 41 youth and adult correctional facilities, 44 camps, and 5 adult prisoner/mother facilities. The CDCR contracts for 19 adult parolee service centers and 13 adult community correctional facilities and leases beds at 3 county jails. The CDCR also operates 192 youth and adult parole units and sub-units, 4 parole outpatient clinics, and 2 correctional training centers. In addition, the CDCR has 10 regional accounting offices and leases almost two million square feet of office space.
The CDCR operates 4 licensed general acute care hospitals, 1 licensed skilled nursing facility, 1 hospice program for the terminally ill, 16 licensed correctional treatment centers, 5 hemodialysis clinics, and outpatient housing units at most correctional facilities.
The CDCR's infrastructure includes more than 40 million square feet of building space on more than 27,000 acres of land (42 square miles) statewide.
MAJOR PROJECT CHANGES Back to Top
- The Governor's Budget proposes $94.2 million General Fund for fourteen continuing projects. This amount includes $26.9 million for four mental health projects in response to the Coleman and Farrell courts, $26.1 million for water and wastewater projects at Chuckawalla Valley State Prison, Mule Creek State Prison, and Sierra Conservation Center, $15.3 million to continue the replacement of dormitory housing at California Rehabilitation Center, $8.2 million for two projects at Folsom State Prison for critical improvements to the electrical wiring in Building 5 and to complete the conversion of existing office space, $7.2 million for cell front conversions at California Medical Facility and Correctional Training Facility to improve security in their administrative segregation units. This amount also includes $10.5 million for minor projects and budget packages.
- The Governor's Budget proposes $5.9 million General Fund for two new projects. This amount includes $5.8 million to replace the heating, ventilation, and air conditioning system at Ironwood State Prison and $113,000 to install a bar screen in the wastewater discharge line at California Rehabilitation Center.
- The Governor's Budget proposes $136.3 million lease-revenue bonds for the completion of the Condemned Inmate Complex at San Quentin State Prison.
SUMMARY OF PROJECTS Back to Top
Provides expenditures for each major and minor capital project funded in this state agency's budget for the past, current, and budget years. The project phase and fund classification are also identified. The Standard Footnotes key can be accessed by clicking on any footnote link.
60 |
CAPITAL OUTLAY |
|
|
|
|
Major Projects |
|
|
|
60.26 |
NORTHERN CALIFORNIA YOUTH CORRECTIONAL CENTER, STOCKTON |
$2,220 |
|
$- |
|
$936 |
|
60.26.006 |
Core Treatment Facility |
2,220 |
Sg |
- |
|
- |
|
60.26.269 |
Sexual Behavior Treatment Program Counseling Building #1 (NACYCF) |
- |
|
- |
|
419 |
Cg |
60.26.270 |
Sexual Behavior Treatment Program Counseling Building #2 (NACYCF) |
- |
|
- |
|
517 |
Cg |
61.01 |
STATEWIDE |
$1,289 |
|
$97,906 |
|
$627,467 |
|
61.01.001 |
Budget Packages and Advance Planning |
1,104 |
Sg |
2,000 |
Sg |
3,000 |
Sg |
61.01.202 |
Small Management Exercise Yards (MCSP, WSP, RJD) |
- |
|
2,465 |
Cg |
- |
|
61.01.203 |
Small Management Exercise Yards |
- |
|
911 |
PWg |
25,407 |
PWCg |
61.01.400 |
Modulars for Farrell Related Program Space |
- |
|
6,500 |
PWCg |
- |
|
61.01.751 |
Infill (Phase I) |
- |
|
10,000 |
PWn |
140,000 |
Cn |
61.01.752 |
Re-Entry (Phase I) |
- |
|
10,000 |
PWn |
142,200 |
Cn |
61.01.754 |
Medical/Mental/Dental (Phase I) |
- |
|
16,030 |
PWn |
66,860 |
PWCn |
61.01.759 |
Habitat Conservation Plan |
185 |
Vg |
- |
|
- |
|
61.01.998 |
Existing Prison Facilities-Renovate/Improve/Expand Infrastructure Capacity |
- |
|
50,000 |
PWCg |
250,000 |
PWCg |
61.03 |
CALIFORNIA CORRECTIONAL CENTER, SUSANVILLE |
$2,234 |
|
$51,418 |
|
$- |
|
61.03.023 |
Wastewater Treatment Plant Modifications |
2,234 |
APg |
51,418 |
WCn |
- |
|
61.04 |
CALIFORNIA CORRECTIONAL INSTITUTION, TEHACHAPI |
$5 |
|
$28,492 |
|
$- |
|
61.04.040 |
Wastewater Treatment Plant Renovation |
5 |
Wn |
28,492 |
WCn |
- |
|
61.05 |
CORRECTIONAL TRAINING FACILITY, SOLEDAD |
$- |
|
$405 |
|
$498 |
|
61.05.038 |
Solid Cell Fronts |
- |
|
405 |
Pg |
498 |
Wg |
61.06 |
DEUEL VOCATIONAL INSTITUTION, TRACY |
$32,366 |
|
$41,934 |
|
$- |
|
61.06.029 |
Groundwater Treatment/Non-Potable Water Distribution System |
29,957 |
Cg |
700 |
Cg |
- |
|
61.06.030 |
New Wastewater Treatment Plant |
2,175 |
WCg |
36,955 |
Cn |
- |
|
61.06.034 |
New Electrical Power Substation |
234 |
Pg |
3,874 |
WCg |
- |
|
61.06.035 |
Solid Cell Fronts |
- |
|
405 |
Pg |
- |
|
61.07 |
FOLSOM STATE PRISON, REPRESA |
$410 |
|
$370 |
|
$8,151 |
|
61.07.029 |
Convert Officer and Guards Building to Office Space |
410 |
Pg |
370 |
Wg |
6,275 |
Cg |
61.07.107 |
Renovate Branch Circuit Wiring, Building #5 |
- |
|
- |
|
1,876 |
WCg |
61.08 |
CALIFORNIA INSTITUTION FOR MEN, CHINO |
$319 |
|
$6,863 |
|
$- |
|
61.08.037 |
Electrified Fence (East Facility) |
-19 |
Cg |
- |
|
- |
|
61.08.049 |
Solid Cell Fronts |
338 |
Wg |
6,863 |
Cg |
- |
|
61.09 |
CALIFORNIA MEDICAL FACILITY, VACAVILLE |
$6,932 |
|
$1,061 |
|
$6,688 |
|
61.09.036 |
Mental Health Crisis Beds |
3,638 |
Cn |
1,061 |
Cn |
- |
|
61.09.038 |
Solid Cell Fronts |
296 |
Wg |
- |
|
6,688 |
Cg |
61.09.040 |
Intermediate Care Facility |
1,189 |
WCg |
- |
|
- |
|
61.09.041 |
Intermediate Care Facility |
1,809 |
Pg |
- |
|
- |
|
61.10 |
CALIFORNIA MEN'S COLONY, SAN LUIS OBISPO |
$6,101 |
|
$48,640 |
|
$- |
|
61.10.036 |
High Mast Lighting (East Facility) |
1,040 |
Cg |
5 |
Cg |
- |
|
61.10.047 |
Wastewater Collection Treatment Upgrade |
4,419 |
Cn |
3,870 |
Cn |
- |
|
61.10.049 |
Potable Water Distribution System Upgrade |
75 |
Cg |
33,488 |
Cg |
- |
|
61.10.052 |
Electrified Fence (East Facility) |
567 |
Cg |
162 |
Cg |
- |
|
61.10.101 |
Central Kitchen Replacement |
- |
|
10,522 |
WCgn |
- |
|
61.10.102 |
Locked Observation Unit |
- |
|
593 |
Cg |
- |
|
61.12 |
SAN QUENTIN STATE PRISON, SAN QUENTIN |
$1,072 |
|
$54,761 |
|
$428,745 |
|
61.12.027 |
Condemned Inmate Complex |
1,072 |
Wn |
5,889 |
Wn |
331,275 |
WCn |
61.12.030 |
Lethal Injection Chamber |
- |
|
182 |
Cg |
- |
|
61.12.031 |
Central Health Services Facility |
- |
|
48,690 |
PWCn |
97,470 |
Cn |
61.13 |
CALIFORNIA INSTITUTION FOR WOMEN, FRONTERA |
$1,893 |
|
$423 |
|
$601 |
|
61.13.015 |
Acute/Intermediate Care Facility |
1,893 |
Pg |
- |
|
- |
|
61.13.016 |
20-Bed Psychiatric Services Unit |
- |
|
423 |
Pg |
601 |
Wg |
61.15 |
CALIFORNIA REHABILITATION CENTER, NORCO |
$- |
|
$1,722 |
|
$15,449 |
|
61.15.027 |
Potable Water System Improvements |
- |
|
1,722 |
Cg |
- |
|
61.15.035 |
Replace Men's Dorms |
- |
|
- |
|
15,336 |
WCg |
61.15.039 |
Install Bar Screen |
- |
|
- |
|
113 |
PWg |
61.16 |
SIERRA CONSERVATION CENTER, JAMESTOWN |
$701 |
|
$19,121 |
|
$2,579 |
|
61.16.021 |
Effluent Disposal Pipeline |
89 |
Cg |
18,796 |
Cg |
- |
|
61.16.022 |
Electrified Fence |
536 |
Cg |
163 |
Cg |
- |
|
61.16.023 |
Filtration/Sedimentation Structure |
76 |
Pg |
162 |
Wg |
2,579 |
Cg |
61.18 |
MULE CREEK STATE PRISON, IONE |
$156 |
|
$390 |
|
$542 |
|
61.18.008 |
Wastewater Treatment Plant Improvements |
- |
|
390 |
Pg |
542 |
Wg |
61.18.010 |
Enhanced Outpatient Program, Treatment and Program Space |
156 |
Pg |
- |
|
- |
|
61.21 |
CALIFORNIA STATE PRISON, LOS ANGELES COUNTY, LANCASTER |
$183 |
|
$- |
|
$- |
|
61.21.009 |
Enhanced Outpatient Program, Treatment and Program Space |
183 |
Pg |
- |
|
- |
|
61.22 |
CHUCKAWALLA VALLEY STATE PRISON, BLYTHE |
$35,829 |
|
$5,455 |
|
$23,007 |
|
61.22.004 |
Heating, Ventilation, and Air Conditioning System |
35,374 |
Cn |
4,181 |
Cn |
- |
|
61.22.006 |
Wastewater Treatment Plant Improvements |
455 |
Pg |
1,274 |
PWg |
23,007 |
Cg |
61.23 |
CALIFORNIA STATE PRISON, CORCORAN |
$233 |
|
$- |
|
$- |
|
61.23.004 |
Wastewater Treatment Plant Improvements |
233 |
Wg |
- |
|
- |
|
61.27 |
WASCO STATE PRISON, WASCO |
$311 |
|
$1,083 |
|
$- |
|
61.27.002 |
Prescreening Facility at Wastewater Treatment Plant |
311 |
Cb |
1,083 |
Cb |
- |
|
61.30 |
CENTINELA STATE PRISON, IMPERIAL |
$537 |
|
$- |
|
$- |
|
61.30.004 |
Wastewater Treatment Plant Upgrades |
537 |
Wg |
- |
|
- |
|
61.31 |
PLEASANT VALLEY STATE PRISON, COALINGA |
$87 |
|
$7,524 |
|
$- |
|
61.31.001 |
Total Facility |
- |
|
6,127 |
Cn |
- |
|
61.31.002 |
Bar Screen, Prelift Station |
87 |
Cb |
1,397 |
Cb |
- |
|
61.33 |
HIGH DESERT STATE PRISON, SUSANVILLE |
$9,055 |
|
$853 |
|
$- |
|
61.33.003 |
Arsenic Removal from Potable Water Supply |
9,055 |
Cg |
853 |
Cg |
- |
|
61.34 |
IRONWOOD STATE PRISON, BLYTHE |
$- |
|
$- |
|
$5,758 |
|
61.34.004 |
Heating, Ventilation, and Air Conditioning System |
- |
|
- |
|
5,758 |
Pg |
61.35 |
SALINAS VALLEY STATE PRISON, SOLEDAD |
$22,198 |
|
$4,902 |
|
$- |
|
61.35.007 |
64 Bed Mental Health Facility |
21,514 |
WCn |
4,902 |
PWCn |
- |
|
61.35.010 |
Intermediate Care Facility |
27 |
Wg |
- |
|
- |
|
61.35.012 |
Intermediate Care Facility |
657 |
Pg |
- |
|
- |
|
61.37 |
CALIFORNIA STATE PRISON, CORCORAN II |
$- |
|
$17,527 |
|
$- |
|
61.37.001 |
Total Facility |
- |
|
17,527 |
Cn |
- |
|
61.38 |
CALIFORNIA SUBSTANCE ABUSE TREATMENT FACILITY, CORCORAN |
$25 |
|
$4,563 |
|
$- |
|
61.38.001 |
Total Facility |
- |
|
4,563 |
Cn |
- |
|
61.38.002 |
19 Station Hemodialysis Clinic |
25 |
Cg |
- |
|
- |
|
61.39 |
KERN VALLEY STATE PRISON, DELANO (DELANO II) |
$1,863 |
|
$66,393 |
|
$- |
|
61.39.001 |
Maximum Prison with Support Services Facility |
1,733 |
Cn |
66,393 |
Cn |
- |
|
61.39.003 |
Arsenic Removal Water Treatment System |
130 |
Cg |
- |
|
- |
|
61.47 |
CALIFORNIA STATE PRISON, SACRAMENTO, REPRESA |
$2,717 |
|
$1,359 |
|
$- |
|
61.47.002 |
Psychiatric Services Unit/Enhanced Outpatient Care, Phase II |
2,068 |
Cn |
1,359 |
Cn |
- |
|
61.47.005 |
Acute Mental Health Facility |
400 |
Pg |
- |
|
- |
|
61.47.007 |
Enhanced Outpatient Program, Treatment and Program Space |
249 |
Pg |
- |
|
- |
|
|
Totals, Major Projects |
$128,736 |
|
$463,165 |
|
$1,120,421 |
|
|
Minor Projects |
|
|
|
61.14.030 |
Minor Projects |
7,121 |
PWCg |
2,038 |
PWCg |
7,500 |
PWCg |
61.14.035 |
Minor Projects, Farrell Litigation-Program and Treatment Space |
- |
|
3,500 |
PWCg |
- |
|
|
Totals, Minor Projects |
$7,121 |
|
$5,538 |
|
$7,500 |
|
Total Expenditures (All Projects) |
$135,857 |
|
$468,703 |
|
$1,127,921 |
|
FUNDING Back to Top
0001 |
General Fund |
$65,636 |
$138,502 |
$350,116 |
0660 |
Public Buildings Construction Fund |
69,823 |
327,721 |
777,805 |
0747 |
1988 Prison Construction Fund |
311 |
1,083 |
- |
0751 |
1990 Prison Construction Bond Fund |
87 |
1,397 |
- |
Total Expenditures (All Funds) |
$135,857 |
$468,703 |
$1,127,921 |
Refer to the Infrastructure Detail of Appropriations and Adjustments (pdf * - 5K) document for additional information.
|